Saturday, October 15, 2016

Kitchen - Week 19

A little bit of this and a little bit of that...

A little electrical.

The chandeliers and sconce have been installed and are mostly working, though there's an issue with the the 3-way switches (I think one of them isn't...). The outlets, switches, and cover plates are now the correct color (though one of them is different than the others - glossy vs matte). The electrical hookup finally got figured out for the range, but we've yet to test it out. and the other appliances are in a similar state.

A little plumbing.

Supply, waste, and vent lines are hooked up in the basement, but not under the sink. The water line to the fridge is hooked up (but untested). The gas line to the range is hooked up as well (again, untested).

A little of the range hood.

There was a bit of head-scratching to remove to cabinet panels that wrap the hood; they need to be off for installation of the hood. There's a big hole in the exterior brick, but the hood liner is prominently on the island, uninstalled. Sounds like some modifications are necessary on various pieces before it will fit right. And ... the reason we got the cabinetry and the liner from the same vendor was to avoid this situation... [shakes head]

If it wasn't for bad luck, I wouldn't have no luck at all...